Update on the Repair and Restoration Efforts at the Integrated Recharge and Recovery Ponds

Information

Department:Operations and Maintenance BranchSponsors:
Category:Action/Info ItemMeeting Workflows:Board O&E Committee Workflow

Attachments

  1. Printout
  2. Presentation

Background

On February 14, 2019, Eastern Municipal Water District’s Integrated Recharge and Recovery (IRRP) Ponds were severely damaged during the region’s major storm event.  During the rainstorm, the IRRP Pond’s internal and external berms were breached allowing large deposits of silt, debris, and driftwood to accumulate within the ponds and surrounding areas.

 

In an effort to quickly repair and restore the ponds and restart Ground Water Recharge Operations, District staff mobilized and began removing silt, debris, and driftwood from the ponds and repairing the berms.

Financial/Strat Plan/Enviro

FINANCIAL IMPACT:

EMWD will pay for 33.7 percent of the total cost and will be reimbursed for the balance through the Hemet-San Jacinto Watermaster.

 

STRATEGIC PLANNING GOAL/OBJECTIVE:

Water Supply and System Redundancy: Develop adaptable buffer supplies, water storage and delivery system improvements to manage uncertain supply delivery conditions and emergency outages.

 

ENVIRONMENTAL IMPACT:

None

Recommendation

This item is informational only.

Meeting History

Mar 28, 2019 3:30 PM  Board Operations and Engineering Committee Regular Meeting
draft Draft
RESULT:DISCUSSED AT COMMITTEE
Apr 3, 2019 9:00 AM  Board of Directors Regular Meeting
draft Draft